Guide · Updated 4 November 2026

Removing a load-bearing wall in a flat or leasehold property: consent, party structures and building regs

The short answerYes, you can usually remove a load-bearing wall in a flat, but the wall is often not yours to touch without the freeholder's written consent (a licence to alter). You'll also need a structural engineer's design, Building Regulations approval, and Party Wall Act notice to the flats the structure is shared with. Allow extra time for the consents.

Why a flat is different from a house

In a house, you own the wall. In a flat you usually don't. Most long leases demise the inside of the flat — roughly plaster inwards — and keep the structure (walls, floors, beams, the frame) with the freeholder or management company. A load-bearing wall in a flat is therefore often part of the building the freeholder owns, and the lease will say you can't alter it without their written consent.

The second difference is who else the structure carries. In a house, a beam carries your own floors and roof. In a flat it can be carrying the flat above, and the wall you want to remove may be helping hold up the whole stack. That makes the engineering, the fire separation and the neighbour notices all more involved than a kitchen knock-through in a semi.

Step one: the freeholder's consent (licence to alter)

Read your lease before you ring an engineer. Almost every long lease has an alterations clause. Some say structural alterations are not allowed at all (an 'absolute' covenant); more commonly they say you need the landlord's prior written consent, which is not to be unreasonably withheld. Where consent can be given it is usually documented in a licence to alter: a formal deed between you and the freeholder setting out what you may do and on what conditions.

Expect the freeholder — or their managing agent — to ask for the structural engineer's drawings and calculations, a method statement for the temporary works, evidence of the contractor's insurance, and confirmation that Building Regulations approval is in hand. The freeholder's own surveyor and solicitor will usually review the pack, and their fees are normally payable by the leaseholder on top of the licence itself. Ask the managing agent for their scale of charges before you commit, and allow weeks rather than days for the process.

Doing structural work without the consent your lease requires is a breach of the lease. At best it means retrospective consent and fees; at worst it surfaces when you sell, the freeholder can demand reinstatement, and in serious cases it puts the lease itself at risk. It is far cheaper to ask first.

Step two: the structural engineer

The engineer's job in a flat is the same as in a house — work out what the wall carries and design a beam, posts and bearings to carry it — but with more at stake. They need to understand how the building is put together (a Victorian conversion, a 1960s concrete frame and a modern timber-frame block all behave differently), what sits above the wall, and how the load gets down to the ground through the flats below. In a converted house that was never designed as flats, a wall is often doing more than it looks.

The engineer's calculations and drawings are also what the freeholder, building control and any party wall surveyor will ask to see, so get them done properly and early. The fee is typically £350–£1,000 for a domestic beam, as in a house.

Step three: Party Wall Act notices — walls, floors and ceilings

The Party Wall etc. Act 1996 covers 'party structures', not just party walls. The floor and ceiling between you and the flats above and below count as a party structure under the Act, as does any wall shared with the flat next door. Cutting a beam or padstone into any of them, or inserting a beam whose bearing affects them, is notifiable work.

In practice that can mean serving a party structure notice on the owners of the flat above, the flat below and the flat alongside — and usually on the freeholder as well, since they own the structure of those flats. Notice must be served at least two months before the work starts. If everyone consents in writing, no surveyors are needed. If anyone dissents or doesn't reply within 14 days, surveyors are appointed to agree an award, which adds time and typically £700–£1,000+ per appointed surveyor.

As with a house, the practical advice is to talk to the neighbours first. People who have had the work explained — and who know an engineer has designed it and building control will inspect it — consent far more often than people who find a legal notice on their mat.

Step four: Building Regulations — structure, fire and sound

Structural work always needs Building Regulations approval, flat or house. In a flat, two more parts of the regulations come into play. Fire: each flat is a separate fire compartment, so the walls and floors between flats have to keep their fire resistance, and the new steel itself needs protecting — usually fire-rated plasterboard boxing or intumescent paint. If the wall you are removing is part of a protected escape route or a compartment wall, the design has to maintain that separation. Sound: the floors and walls between dwellings have to meet sound insulation standards, so a beam cut into a separating floor can't be allowed to become a path for noise.

Building control will want the engineer's calculations and will inspect the bearings, padstones and fire protection before the beam is boxed in. The completion certificate at the end is what the freeholder, your buyer's solicitor and your mortgage lender will all ask to see. Application fees run £300–£1,000 depending on the council or approved inspector and the number of inspections.

The order to do things in

Because each consent depends on the one before, the sequence matters more than it does in a house:

  • Read the lease, then write to the freeholder or managing agent to say what you intend — before spending money on drawings
  • Survey, then the structural engineer's calculations and drawings
  • Licence to alter application to the freeholder, with the engineer's pack, method statement and insurance
  • Building Regulations application — full plans is usually the safer route in a flat, because the freeholder will want to see approval before signing
  • Party structure notices to the flats above, below and alongside, and to the freeholder — two months, or sooner with written consent
  • Install: props and needles in, wall out, beam in, bearings packed, fire boarding — typically one to two days on site for a single beam
  • Building control final inspection and completion certificate; send a copy to the freeholder to close out the licence

What it costs in a flat

The steelwork itself is priced the same way as in a house: £1,800–£4,500 including the beam and installation for a typical single opening, with larger openings and goalpost frames running £5,000–£10,000. Add £350–£1,000 for the engineer and £300–£1,000 for building control.

What a flat adds on top is the paperwork: the licence to alter, with the freeholder's surveyor's and solicitor's fees, and party structure notices to more neighbours than a house ever has. Those fees are set by the freeholder and the surveyors, not by us, so ask for them up front. Access matters too — carrying a beam up three flights of a communal stair can mean a beam spliced from bolted sections and assembled in the room, which adds fabrication cost.

How we help

We survey the flat, tell you honestly whether the wall is structural and what it's carrying, and work with the structural engineer on a design the freeholder and building control can approve. We can serve the party structure notices on your behalf and give the managing agent the method statement and insurance details they'll ask for. On the day, our team props, removes the wall, installs the beam and protects it, then hands over the paperwork for building control's completion certificate.

Related questions

Can the freeholder refuse to let me remove a load-bearing wall?

If your lease has an absolute bar on structural alterations, yes — consent is at their discretion. If the lease says consent is not to be unreasonably withheld, they can attach reasonable conditions (an engineer's design, building control approval, insurance, reinstatement if something goes wrong) but can't refuse for no good reason. Either way, start with the lease.

Does the flat below need to be told?

Usually, yes. The floor between you is a party structure under the Party Wall Act, so if the work affects it — a beam bearing on a wall that continues down into their flat, or any cutting into the separating floor — notice is required. Your engineer will confirm exactly what the work touches.

Is the wall even mine to remove?

Check the lease plan and the demise clause. Many leases demise only the internal, non-structural parts of the flat, with load-bearing walls retained by the freeholder. That is exactly why the licence to alter exists: it is the freeholder giving permission for work to their structure.

Do I need planning permission to knock through in a flat?

Not for an internal alteration in most cases, because planning controls external appearance and use. The exceptions are listed buildings, where internal work needs listed building consent, and jobs that also create a new external opening. Freeholder consent and Building Regulations are the ones that always apply.

How long does the whole thing take in a flat?

Longer than a house, because the licence to alter and the party structure notices run in series with the engineering rather than alongside it. The site work is still one to two days for a single beam; the consents in front of it are what take the time, so start them early.