Building notice or full plans for a wall removal: which should you use?
What is the difference?
With full plans, you submit drawings and calculations and the building control body checks them before work starts. GOV.UK says you can expect a decision within 5 weeks, or 2 months with your consent.
With a building notice, nothing is approved in advance. GOV.UK says it is only for smaller projects, you can start work 2 days after submitting it, and you do not get formal approval like you do with full plans.
Which suits a single wall removal?
Usually a building notice. The design is a beam and two padstones, the engineer's calculations exist before the work starts, and the inspector checks them against what is built. It avoids a wait of several weeks for a single opening.
The risk is that nothing is checked until the inspector visits. If they disagree with something, it is put right on site. With a proper engineer's design that is rare.
When is full plans the better choice?
Full plans earns its extra time when:
- The structural work is part of a bigger project, such as an extension or loft conversion
- There are several beams, a goalpost frame or new foundations
- Fire escape routes change, for example an open-plan ground floor in a three-storey house
- Your lender, a freeholder or a buyer wants to see approval before the work starts
- You want the design checked before the steel is ordered
How long does each one last?
Manchester City Council says its building notice is valid for three years, and that it may ask for plans and calculations later. Whichever route you use, councils expect notice before work starts: Manchester asks for at least two working days, and Salford says work must not start until two days after the commencement notice.
What do you get at the end?
A completion certificate, either way. GOV.UK says that with full plans you will usually get one within 8 weeks of completion, as long as the work complies. Salford City Council notes that a completion certificate is only issued once a final inspection has been requested, so make sure someone books it.
Keep it safe. Salford also points out that insurers, mortgage companies and solicitors may ask for copies.
What if the wall is already gone?
Then neither applies. Work done without approval goes through regularisation, which GOV.UK says is available only from a local authority, and only for work carried out after 11 November 1985. You may have to open up the work and make alterations before a regularisation certificate is issued.
Can a private approver do it instead of the council?
Yes, for both new work routes. You can use a registered building control approver instead of the council, and they notify the local authority with an initial notice. Regularisation is the exception: only the council can do it.
Related questions
Is a building notice cheaper than full plans?
Fees depend on the council or approver and the number of inspections. For a domestic wall removal, budget £300–£1,000 for building control either way.
Can I switch from a building notice to full plans?
Talk to the building control body. Where a project grows, for example the wall removal turns into an extension, a full plans application for the larger scheme often makes more sense.
Who submits the application?
Either you or your contractor on your behalf. We handle the application, book the inspections and leave the steel visible until building control have seen it.